Latest Updates

Latest Update 31 March

Works to the Southern Roundabout were completed under road closures 26-29 March. The works were completed ahead of time with traffic flows able to use the new road layout from Sunday evening 28 March. New link roads construction, kerbing, surfacing, signage and roadmarking works were carried out over the weekend. Further surafacing and roadmarkings to

Read More »

Latest Update 01 March

Latest Update 01 March Works to connect the new Northern Roundabout to the existing A140 carriageway were completed under road closures 26Feb to 01 March. New link roads construction, kerbing, surfacing, signage and roadmarking works were completed ahead of time allowing traffic to be diverted onto the new roundabout on Sunday evening 28 Feb.

Read More »

ADVANCE WARNING OF A140 ROAD CLOSURES

There will be a full road closure in place on the A140 from the B1077 (top of the Brome triangle) down to Castleton Way in Yaxley from 20:00hrs on Friday 26 February until 05:00hrs on Monday 01 March 2021. The closure will allow construction work to take place to connect the existing A140 carriageway to

Read More »

Latest Works Progress 05 Feb 21

Northern Roundabout:  Surfacing Works are well progressed with base and binder courses completed. Final surface course and roadmarkings will be installed as connections made to the existing A140 carriageway. This is currently scheduled for the weekend of 26th February to 01st March 2021. Footpaths & verges – path construction works are well progressed and topsoiling

Read More »

Latest Works Progress 29 Jan 2021

Northern Roundabout:  Surfacing Works are well progressed with base and binder courses completed. Final surface course and roadmarkings will be installed as connections made to the existing A140 carriageway. This is currently scheduled for the weekend of 26th to 28th February 2021. Footpaths & verges – path construction works are currently ongoing and topsoiling to

Read More »

Latest Works Progress

Northern Roundabout:  Surfacing Works are well progressed with base and binder courses completed. Final surface course and roadmarkings will be installed as connections made to the existing A140 carriageway. This is currently scheduled for the weekend of 12th to 14th February 2021. Footpaths & verges – path construction works are currently ongoing and topsoiling to

Read More »

Latest Works Progress:

Latest Works Progress: Northern Roundabout Surfacing works to roundabout and link roads approaching completion Drainage & kerbing works complete Footpath & verge works progressing well Tie-ins to existing A140 carriageway planned for Feb 2021 – exact dates tbc. Southern Roundabout Preparation of Sub Base to roundabout and link road progressing well Drainage & kerbing works

Read More »

Northern Roundabout

Sub Base preparation works approaching completion with surfacing works due to be carried out Tuesday 15th to Wednesday 23rd December. (Further works from 04 January 2021)

Read More »

Southern Roundabout

Over 1000 Tonnes of aggregate have been imported to form the Sub Base to the new carriageway / Drainage works continuing / Kerbing works have commenced.

Read More »

Site Flyovers

These two drone flyovers show both roundabouts progressing well and clearly taking shape with the new link road to the B1077 clearly visible. We’re continuing to make good progress on site.  We’ll share more videos of our work in due course.  

Read More »

Did you know

Did you know – As we are building near a disused WW2 airfield we occasionally find interesting artefacts in the ground (we’ve safely disposed of any ammunition). This is an air bottle jettisoned from an aircraft and would have been used by aircrew at the rear of a plane to breath at altitude.

Read More »

Meet our partners

The scheme brings together a range of skills that are required to deliver the scheme. Here you can find out more about some of the other companies assisting Interserve Construction as we work on the scheme. A range of partners covering various disciplines have come together as they partner with us and help to deliver

Read More »

Covid update

Suffolk County Council and Interserve Construction are constantly reviewing the latest Government guidance to ensure safe working practices. Our site offices are Covid compliant whilst our site operatives are maintaining social distancing practices.

Read More »

Southern roundabout

We’ve moved thousands of tonnes of soil to help build up the base for the new southern roundabout and road. The new roundabout is already taking shape along with the new stretch of road.

Read More »

Northern roundabout

We’re continuing to make good progress on the northern roundabout and link road with the road starting to take shape. Surfacing works are due to take place next month. Noise mitigation measures are in place for local properties.

Read More »
Scroll to Top