Latest Works Progress 29 Jan 2021

Northern Roundabout:
 Surfacing Works are well progressed with base and binder courses completed. Final surface course and roadmarkings will be installed as connections made to the existing A140 carriageway. This is currently scheduled for the weekend of 26th to 28th February 2021.
  • Footpaths & verges – path construction works are currently ongoing and topsoiling to verges underway
  • Traffic Signs – works have commenced to install sign bases and posts, sign plates will be installed immediately before traffic switch
  • Drainage – main drainage completed and additional filter drain installation works ongoing
Link Road:
  • Footpaths & verges – path construction works are currently ongoing and topsoiling to verges underway
  • Traffic Signs – works have commenced to install sign bases and posts, sign plates will be installed immediately before traffic switch
  • Drainage – main drainage completed and additional filter drain installation works ongoing
  • Vehicle Restraint System due for installation early Feb 21
Southern Roundabout:
  • Earthworks – earthmoving completed and preparation of Sub Base road construction well progressed
  • Drainage works – ongoing and well progressed,
  • Surfacing Works have commenced to eastern arm of roundabout / connection to Castleton Way